GDRM-STATION NORDLOHNE

GDRM-STATION NORDLOHNE

Innovative natural gas feed-in: L/H gas conversion project

The planning and construction supervision of the gas pressure regulation and measurement system for the feed-in of natural gas as part of the L/H gas conversion is a comprehensive project that includes the technical design and dimensioning of the system, the planning of the buildings and open spaces, as well as the pipeline and steel construction. Furthermore, the long-distance pipeline connection, the EMSR technology including the specifications for the control technology and the integration of the systems into the higher-level control system are planned. The integration of the GDRM plant into existing systems, the creation of technical specifications for all relevant components and the creation of a cost calculation are also part of the project. In addition, the project includes the preparation of all approval documents such as the building application and §5 notification in accordance with GasHdrLtgV as well as the coordination of the accompanying landscape conservation planning. In addition, general contractor tenders for pipeline construction and EI&C technology as well as pipeline construction are prepared, participation in contract award negotiations and the processing of supplements and change proposals. Finally, the project also includes planning and construction supervision during the construction and commissioning of the plant.

The client for this project is Open Grid Europe GmbH.

Scope of supply

  • Technical design and dimensioning of the GDRM system
  • Planning the buildings and open spaces
  • Planning of pipeline construction and steel construction
  • Planning the transmission line connection
  • Planning of the EI&C technology including the specifications for the control technology and integration of the systems into the higher-level control system
  • Planning the connection of the GDRM system to the existing systems
  • Preparation of technical specifications for all relevant components
  • Preparation of a cost calculation
  • Preparation of all approval documents, e.g. building application and §5 notification according to GasHdrLtgV
  • Coordination for the preparation of the accompanying landscape conservation planning
  • Preparation of general contractor tenders for pipeline construction and EMSR technology, as well as pipeline construction
  • Participation in the award negotiations
  • Processing supplements and proposed changes
  • Planning during construction
  • Construction supervision during construction and commissioning of the system

CUSTOMER

Open Grid Europe GmbH

Gib hier deine Überschrift ein